Deployment is the part that decides whether the project succeeds
Buying a robot is a purchasing decision. Deploying one is an operational change. The vehicles that fail in the field almost never fail because of hardware; they fail because the flow was never redesigned around them, the safety assessment was treated as paperwork, or the software seam to the WMS was discovered in week six.
The plan below is the sequence that consistently works on in-plant pallet flows, whether the site is installing two vehicles or twenty. It runs from the first site visit to the point where the fleet is a normal part of operations - and each phase has a defined deliverable, so the project can be reviewed rather than merely reported.
Phase 1 - Survey and feasibility (2 to 3 weeks)
The purpose of this phase is to establish whether automation is the right answer for this flow at all, before anyone quotes a number.
Deliverables: a layout marked with the proposed routes, a measured minimum aisle width, a pallet population audit, a flow volume table, and a rough order-of-magnitude business case.
The site survey is the phase where most projects are saved or lost. Walk the route physically. Measure the narrowest point with a tape, not from a drawing. Photograph every doorway, threshold, ramp and floor joint. Note where light levels drop, where Wi-Fi is weak, and where pedestrians routinely cross.
The pallet audit is the second critical input. Sample 50 to 100 pallets across the real mix, including damaged ones, and record dimensions, overhang, condition and type - standard, cruciform (Chuanzi-style), nine-leg Euro, block. A vehicle's pickup reliability against this sample, not against a perfect pallet, is what determines throughput.
Exit criteria: an agreed flow scope, a vehicle class recommendation, and a decision to proceed to detailed design.
Phase 2 - Safety and compliance design (2 to 4 weeks, parallel with Phase 1 output)
This deserves its own phase because it cannot be bolted on afterwards.
Any driverless industrial truck sharing space with people is machinery, and it is assessed as such. The relevant framework is ISO 3691-4 for driverless industrial trucks and their systems, with EN 1175 governing electrical requirements in the European context and ANSI/ITSDF B56.5 applying in North America. CE marking in Europe requires a technical file, a risk assessment and a declaration of conformity - the latter signed by the manufacturer, not by the integrator.
What this means in practice:
A documented risk assessment covering each operating zone: what can a person do in this area, what can fall, what can be occluded, what happens at a blind corner or a doorway.
A safety functions list with performance levels: protective stop on detection, speed limitation by zone, load stability monitoring, emergency stop, audible and visual warning at junctions.
Zone definition. Robot-priority areas, shared areas with speed limits, and exclusion areas. Most sites find that clearly zoning dense aisles as robot-priority is both safer and faster than mixing traffic at close quarters.
A pedestrian interface design. Where do people cross, how are they warned, what is the rule when a person enters a robot zone.
Exit criteria: a signed risk assessment, a zone map, and confirmation that the safety functions match the assessment - not just a brochure claim of "advanced safety".
Phase 3 - Integration design
The robot is a transport device. Its value comes from the task flow that drives it, and that flow lives in software you already own.
Map the seam explicitly. In most plants there are three candidate layers:
WMS / MES / ERP. The preferred integration is task-level: the system issues a transport order ("move pallet 4471 from receiving lane 3 to line-side position B12"), the fleet manager accepts it, dispatches a vehicle and reports completion. This requires a documented API on both sides - REST or a message queue - and a clear owner for the mapping between location identifiers in your system and physical positions on the floor. That mapping is where integration projects quietly overrun, so define it in Phase 3, in writing.
PLC and conveyor handshake. Where the vehicle interacts with a conveyor, a door, a lift or a transfer station, the interface is usually digital I/O or Modbus TCP, with a defined handshake sequence: request, ready, transfer, complete, fault. Specify timeout behaviour for each step, because the interesting failures happen when one side believes the transfer succeeded and the other does not.
Elevator control. Multi-floor facilities need the vehicle to call a lift, enter, select a floor and exit. This is available as an option on platforms designed for it, and it typically requires cooperation with the lift vendor. Start that conversation in Phase 3, not during commissioning; lift interfaces are the single most common cause of schedule slip in multi-floor deployments.
Exit criteria: an interface specification signed by your IT/OT owner and the supplier, with the identifier mapping table attached.
Phase 4 - Pilot on one real flow (4 to 6 weeks)
A pilot is not a demonstration. A demonstration shows the vehicle moving a pallet on a clean floor. A pilot runs one production flow, on real pallets, for long enough to see what happens when something goes wrong.
Design the pilot so it can fail visibly:
Choose the flow that is both high-volume and moderately difficult - not the easiest loop.
Run it across at least two shifts, including a night shift if you operate one.
Instrument the six metrics below from day one.
Agree in advance what happens to the pilot flow when a vehicle is down: who reverts it to manual, and how quickly.
The six metrics:
|
Metric |
Why it matters |
|
Trips completed per hour, by shift |
Reveals the real duty cycle, not the best case |
|
Pickup success rate on real pallets |
The single biggest driver of intervention cost |
|
Interventions per 100 trips, and recovery time |
Directly predicts the labour you must retain |
|
Availability (productive hours / scheduled hours) |
The number to hold the supplier to contractually |
|
Charge events per shift and energy per trip |
Validates the charging design and tariff assumptions |
|
Task completion latency |
Measures whether the software seam actually works under load |
Exit criteria: a pilot report with those six numbers, a decision on fleet size based on measured throughput, and a documented exception list - the pallets, positions and situations the vehicle should not be sent to.
Phase 5 - Production rollout, in waves
Do not commission the whole fleet in one weekend. Roll out in waves of two to four vehicles, each wave adding one new flow and one new zone. This preserves a simple property that makes the project governable: at any moment, at most one part of the operation is in change.
Each wave repeats a short version of Phase 4: run the new flow for a week, check the six metrics, fix the exception list, then move on. Commissioning support from the supplier should be scheduled around the waves, not compressed into a single visit.
Operational readiness matters as much as hardware readiness. Before each wave, confirm:
Floor marking and signage are in place for pickup and drop zones.
Charging positions are clear and assigned, with no vehicle-left-blocking-a-door habits forming.
Operators have been trained on the call interface and on exception recovery.
A named person owns map maintenance and knows when a rack change requires a mapping update.
Spare parts and the service contact are actually known to the shift supervisor, not only to the project manager.
Phase 6 - Scale, and make it boring
The mark of a successful deployment is that nobody talks about the robots anymore. Getting there requires three habits:
Review the KPIs monthly, not annually. Availability drift, rising intervention counts and growing exception lists are the three early indicators of a system slowly becoming manual again. A monthly thirty-minute review catches them while they are cheap to fix.
Keep the map current. Every rack relocation, new staging lane or removed pillar is a mapping event. Assign ownership. A stale map in a high-density area produces exactly the symptoms people misdiagnose as "the robot is unreliable".
Grow the fleet along the flow, not along the catalogue. Add vehicles where measured throughput says you are short, and add new vehicle classes only when a genuinely different flow appears - for example, adding compact narrow-aisle units when dense racking enters scope, or heavier counterbalance units when pallet weights rise.
A note on service and support
Deployment risk is mostly service risk in disguise. Three questions determine whether a fleet stays productive:
Where are the spare parts? Local stock versus a shipment from another continent decides whether a scanner fault is a two-hour fix or a two-week outage.
Who answers at 02:00? Confirm support hours and time-zone coverage in writing, and test the channel once during the pilot, at an inconvenient hour.
What is the availability commitment? A contractual figure with a defined measurement method and remedy is worth more than a datasheet percentage.
Reeman provides 24/7 technical support and remote diagnostics across the product line, with service scoped per market. It is worth asking specifically how that maps to your site during the survey, rather than assuming.
Why this sequence, and where Reeman fits
The six phases exist because each one produces an artefact the next one needs: the survey produces the flow scope that the safety design zones, the safety design defines where speed limits apply, the integration spec defines what the pilot can actually test, and the pilot produces the throughput figure that sizes the fleet.
Reeman's product line is built to be deployed in this order rather than bought as a single decision:
Ironhide (1.5-tonne, 2.5 m lift, laser SLAM, LiFePO4, standard and cruciform pallet support) for the mainstream in-plant flow.
Ironhide 3.0 for denser, mixed-traffic sites where obstacle detection latency is the constraint on speed and uptime.
HAMMER 2.0 for cruciform pallet handling with 3D recognition, where pickup reliability sets throughput.
MINI for 1.1 m aisles and high-density layouts that cannot be rebuilt.
Rhinoceros and heavy configurations to 3,000 kg and up to 6 m lift.
Flyboat and chassis platforms for custom top modules and conveyor-linked flows.
All share one navigation and scheduling stack, support optional elevator control, expose an open SDK, and connect to MES, WMS and PLC environments - which means a site can start with one flow and one vehicle class, and expand into a mixed fleet without a second control system.
Founded in 2015 with a 6,000 m² facility, 200+ patents and installations in 55 countries, Reeman works as an OEM: configuration is discussed directly with the people who build the machine, and the service relationship is not layered through a distributor.
FAQ
How long does a typical deployment take?
From survey to a running pilot: 8 to 12 weeks for a single flow. Full rollout of a small fleet across several flows: a further 4 to 8 weeks, depending on how many waves and how much integration work is required.
Do we need to fence off the robot area?
Not necessarily. Zoning, speed limits, detection zones and operating rules usually provide a safer and more flexible solution than fencing, which also blocks the flow. The risk assessment decides.
Can the robot operate in the same aisle as manual forklifts?
Yes, with rules: speed limits, right-of-way conventions, warning devices and defined passing points. Many sites start mixed and migrate to robot-priority as confidence grows.
What if our WMS has no API?
Options include a middleware layer, a PLC-mediated handshake, or a simple call-button interface at fixed stations. The right answer depends on volume and variability, and it should be scoped in Phase 3 rather than improvised during the pilot.
Who signs the CE declaration?
The manufacturer. If a supplier cannot provide a technical file, a risk assessment and a declaration of conformity for the machine as placed on the market, that is a compliance question worth resolving before purchase.
Next step
Send us a layout, your pallet mix and your shift pattern, and we will return a Phase 1 feasibility pack - routes, vehicle class, interface scope and a conservative business case - so the project starts from evidence.