REEMAN Ironhide Connects Warehouse and Production Floors at a Maoming Wire Harness Factory
A real autonomous forklift deployment combining pallet handling, elevator integration and cross-floor material delivery.
|
ACTUAL LOAD |
ONE-WAY ROUTE |
DAILY CROSS-FLOOR TASKS |
|
Approx. 1,000 kg |
Approx. 100 m |
Approx. 65–85 |
Project at a Glance
At an electronic wire harness manufacturing plant in Maoming, Guangdong, China, REEMAN Ironhide 3.0 has been deployed to move palletized wire materials from a warehouse to production workshops on other floors. The forklift automatically performs pickup, route navigation, elevator transfer and final delivery as one coordinated workflow.
The customer reports approximately 1,000 kg of wire materials per transport task, a one-way distance of around 100 meters and 65–85 cross-floor elevator transport tasks per day. Those are operating data provided for this factory-not performance estimates inferred from the videos.
The Customer Requirement: A Repeated Multi-Floor Delivery Job
At this factory, materials do not simply move from one point to another within a single warehouse. Wire materials stored in the warehouse need to reach designated production positions on another floor. That means each task combines pallet pickup, travel through the facility, elevator use and delivery in the workshop.
The goal of the deployment was to reduce the repetitive manual movement involved in this warehouse-to-production route. The project also had to fit an existing building layout: the warehouse pickup area was relatively narrow, and the forklift needed to operate within the available elevator cabin and its entry conditions.

How the Site Was Implemented
1. Pallet pickup in a restricted warehouse area
The forklift approaches the designated pallet location, aligns with the pallet, collects it and departs along the configured route. The challenging part of this area was not only aisle access: the machine also needed sufficient clearance to position its forks and leave with the load.
REEMAN engineers discussed the working geometry with the customer and reserved adequate room for pickup and travel. This was an adjustment to the operating space, not a claim that the forklift can pick up pallets in every narrow aisle without layout assessment.
2. Autonomous travel to the elevator
After pickup, Ironhide follows its mapped route toward the elevator using Laser SLAM navigation. At the elevator waiting point, movement is coordinated with the lift interface; the robot does not simply treat the elevator entrance as an ordinary passage.
3. Elevator integration and cross-floor transfer
A compatible interface coordinates the elevator request and relevant status confirmations. When entry conditions are met, the forklift moves into the cabin. The elevator controller then handles the vertical journey. At the destination floor, the forklift leaves once the required exit conditions have been confirmed.
In practical terms, the robot manages ground navigation and the material-handling task, while the elevator keeps control of its own door operation, vertical motion and protective functions. The exact communication protocol for this installation has not been publicly specified.
4. Delivery to the workshop
On the destination floor, the forklift continues to the designated delivery position, places the pallet and withdraws its forks. The warehouse-to-workshop movement is completed without an operator having to drive the forklift through each stage of the normal task.
Project Conditions and Engineering Boundaries
|
Item |
Maoming customer site |
|
Industry / location |
Electronic wire harness manufacturing / Maoming, Guangdong |
|
Robot |
REEMAN Ironhide 3.0 Autonomous Forklift |
|
Rated forklift payload |
1,500 kg (equipment rating) |
|
Actual load per task |
Approximately 1,000 kg of wire materials |
|
One-way route |
Approximately 100 m, including elevator transfer |
|
Elevator internal dimensions |
Approximately 2.1 × 1.8 × 2.1 m (L × W × H) |
|
Reported daily work |
Approximately 65–85 cross-floor elevator transport tasks |
|
Key site constraint |
Restricted pickup space; clearance coordinated with customer |
Elevator suitability depends on more than the cabin dimensions. The assessment must include door opening, the total entering weight (forklift plus pallet plus material), entry/exit space, thresholds, floor conditions and control-interface compatibility. The Maoming dimensions are site-specific, not universal minimum requirements.
Customer Deployment Videos
The project has been documented in horizontal and vertical formats. The horizontal film records key steps in the on-site engineering acceptance process, including the pickup sequence, elevator entry and exit, and delivery movements. It shows the forklift without the normal production material load; the 1-ton working-load figure comes from the project operating information.
Horizontal Video Guide
|
Time |
Sequence shown |
|
00:00 |
Pickup-positioning sequence |
|
00:11 |
Travel toward the elevator |
|
00:22 |
Elevator entry and cross-floor transfer |
|
00:34 |
Elevator exit and onward navigation |
|
00:54 |
Positioning at the destination |
|
01:06 |
Fork withdrawal and departure |
The chapters refer to the previously reviewed approximately 1-minute-20-second horizontal edit. The edited video length is not the complete transportation cycle time.
What This Case Demonstrates
The measurable scale of the installed task is clear: around 1,000 kg per delivery, a 100-meter one-way route and roughly 65–85 cross-floor transport assignments daily. The practical value comes from connecting warehouse pickup, lift travel and workshop delivery into a repeatable operating process.
It also shows why a real deployment is an engineering project, not just a product specification. Pickup geometry, the combined load entering the elevator, doorway clearance, interface compatibility and the customer's day-to-day traffic pattern all have to be considered at the site.
No specific labor-cost saving, percentage productivity improvement or investment payback is claimed here without a measured manual-handling baseline and full project-cost information.
Frequently Asked Questions
Q: What does the forklift transport at this customer site?
A: Palletized wire materials used in electronic wire harness manufacturing. The normal material load is approximately 1,000 kg per task.
Q: Does 65–85 daily tasks mean 65–85 complete round trips?
A: No. The number refers to reported cross-floor elevator transport tasks. A separate count of complete return journeys has not been confirmed.
Q: Can the forklift call and use the elevator without a driver?
A: In a compatible integration, the robot task system coordinates elevator service and entry/exit conditions with the elevator interface. The elevator controller remains responsible for its own operation and safety functions.
Q: Will the same setup work with any existing factory elevator?
A: Not automatically. Engineers must verify the combined weight, cabin and door opening, thresholds, available operating space and elevator-control compatibility for each installation.
Q: How was the narrow warehouse pickup area handled?
A: REEMAN engineers coordinated with the customer to reserve the clearance needed for pallet approach, fork alignment, pickup and loaded departure.
Q: Why does the horizontal film not show a full production load?
A: It was recorded for on-site engineering acceptance and shows the movements and elevator coordination. The approximately 1-ton normal load is reported project operating information, not a weight measured from the film.
Conclusion: A Working Route Between Storage and Production
The Maoming wire harness project provides a practical reference for manufacturers whose material flow crosses factory floors. REEMAN Ironhide links pallet handling, mapped navigation and elevator coordination into a routine warehouse-to-production workflow, while the on-site engineering addresses real constraints at the pickup point and elevator.
For a comparable project, the first step is a site assessment covering pallet size, actual load, pickup and delivery positions, elevator specifications and expected daily transport frequency.